Track

Project title
Client
Scope of works
Deadline
1 465 000 m3 of earth movement
Railway line Mechrra- Bechar on 141 km ANESRIF / SNTF Reinforced concrete
Achievement of 02 stations
23 months
REALIZATION IN PROGRESS
Track-doubling and modernization of the installations of railway line Setif- Al Ghourzi on 78 km ANESRIF / SNTF 698 266 m3 of earth movement, 2 260 m3 of reinforced concrete 25 months
Carrying out the railway line Tissemsilt – Boughzoul on 139 km ANESRIF /SNTF Embankments: 10 132 918 m3
Spoil: 6 821 563 m3
Foundation layer: 1.058.551 m3
Sub-ballast layer: 481 960
2 stations (Tissemsilt and Sidi Ladjal)
43 months
Carrying out the railway Arzew ZI –Arzew City on 4 km ANESRIF/ SNTF 15 months
Carrying out of new line Tougourt – Hassi Messaoud on 154 km ANESRIF/ SNTF Embankments: 2 739.072 m3
Spoil: 2.257 620 m3
Foundation layer: 806.650 m3 Sub-ballast layer: 508.600 m3
Hydraulic structure: 2 063 ML
48 months